LOCAL
MINING LICENCE
BASE
ON THE LAW
Decree of home minister num 26, 1994, 26 march 1994 about
guidance of mining material level c for mining business
UNIT
Office of mining and mineral resource muarojambi regency
PROCEDURAL
Making the request in written to the regent of muarojambi c/q
the head of mining and mineral office with enclosing the
needed requirements.
REQUIREMENTS
1. Map region / location
2. recommendation letter from the head district
3. recommendation letter from the head village
4. identity card ( copied )
5. certificate of establishing company ( for legalized company
)
6. AMDAL / UKL-UPL document
7. Planning of production
8. A receipt for reclamation quarantee
TIME
3 ( Three) days of working day
COST
Legal – size fee Rp. 35.000
VALID
ISSUE
2 Years
THE
KEEPER’S OBLIGATION
1. He must not the activities outside of determined area given
2. License must not be taken over over to others without
giving information first to the regent
3. The capacity of production must not produce more than the
cubication that is determined
4. The company must pay the retribution of mining material
according to the tariff that has been ruled in region decree
5. Mining activities must keep the sustainable of mining area
6. The company must do the esthetic arrangement of mining area
7. If in 2 month started the date issued, company doesn’t run
the actvities so the license considers unvalid
SANCTION
1. Warning In Written
2. Frozen The Lisence
3. Drawn Out The Lisence